Sprint Summary Report

Short summary of Sprint 20 - ekar Digital

Sprint Start Date : 03-08-2020 .

Sprint End Date : 31-08-2020

Total Working days: 20

Metrics:

Velocity:

Burndown:

Burndown chart

Summary:

Points Committed - 1136 , Points Delivered - 936

Major stories delivered:

Telemetry migration to IRIS - https://ekar.atlassian.net/browse/XDS-1312

Stabilization issues from CS and ops team - https://ekar.atlassian.net/browse/XDS-1320

Data issues - Support financial audit - https://ekar.atlassian.net/browse/XDS-1347

Subscription leasing UI - partially completed

Report issues - Android - development completed

Scope Change : Actual points when the sprint started was 1008, we got many stabilizations issues after that and the sprint scope got affected.