Sprint Start Date : 01-07-2020 .

Sprint End Date : 29-07-2020

Total Working days: 20

Metrics:

Velocity:

Burndown:

Summary:

Points Committed - 1856 , Points Delivered - 1912

Major stories delivered:

1.Talon.one - backend - XDS-1277

2. Promotions - Mobile - XDS-920, XDS-1143

3. Braze integration - New attributes and backend support for marketing team to create campaigns .- XDS-1242

4.Subscription leasing - Requirements, brainstorm, Environment setup, Documentation - XDS 1105

5. Report issues - backend - XDS-953

5. Invers Shutdown - XDS-1205

Stories moved out of sprint - Report issues Mobile - XDS 1144, XDS 1059